LEVEL 3 GUIDANCE - Section: 03.202.SHE
Prepared By: D Moore
Approved By: T Chambers
Date: March 1999 - Rev: 3 ISSUE 3

Cold Work Permit

 

This document should be used to support the general requirements of
The Greencore Group Permit to Work 03.200.she.

It is intended to facilitate a "Safe System of Work"
where Cold Work Processes are to be employed.

What is Cold Work?

Cold Work is where heat is the main hazard. We would not permit the use fusion welding, brazing, soldering, or Oxy-acetylene cutting, where petrol was stored equally we must restrict less obvious processes such as metal grinding where sparks are generated or unprotected electric lights in hazardous atmospheres etc.

REMEMBER FIRE IS OUR GREATEST CONCERN, PREVENT IGNITION!

This permit is a higher degree of control than a cleaning and painting permit (03.203.she).

Name of person requiring a Cold Work Permit

Name of company if a contractor

List Cold Work Tools permitted (eg non-sparking tools):

 

 

 

In which areas is Cold Work permitted.

I understand that I am responsible
for the area that I have requested permission to work with cold processes

 

Print Name of person expected to work with cold processes

 

Signature & date

I understand the requirements imposed on me by this Cold Work Permit.

I will request another permit
should I require to use Hot Work Processes in THIS
or any other area of the company.

Name of the Greencore Group Supervisor imposing Cold Work.

The Lower Explosive Limit was unacceptable

Job Title

Signature

By authorising the above Cold Work
I acknowledge that I am responsible
for monitoring he conditions outlined above are being complied with
.

 
  